Project History |
| April 29, 2005 - Rekhi Computer Science Hall Dedication Ceremony |
| January 10, 2005 - Building open for the new semester |
| January 4, 2005 - Elevator passes inspection |
| July 9, 2003 - Contractor arrives on campus |
| May 9, 2003 - Successful Ground Breaking! |
| October 2002 - Michigan Tech Board of Control approves Final Design |
| September 2002 - State authorizes construction |
| August 2002 - Project Program and Schematic Plan submitted to State of Michigan for approval |
| January 2002 - Architectural planning begins |
| December 2001 - Detroit-based SmithGroup, Inc. selected as the architects |
| September 2001 - Process to select an architectural firm begins |
| August 2001 - State authorizes planning for a reduced Center for Integrated Learning and Information Technology
project |
| Janaury 1999 - Planning for the Center for Integrated Learning and Information Technology begins. Initial plans included renovation of Fisher, the Library and additional space for computer science, mathematical science, and physics |